How to build a granny annexe: step by step, from planning to handover
Building a granny annexe in the garden follows the same broad sequence whoever builds it: check the site, choose a planning route, get approval, prepare the ground and connect the services, then put up the building and have it signed off. This guide walks through each step, what it involves and how long it usually takes.
Illustrated from a scale model by The Garden Room & Annexe Guide.
In short
- Most people use a specialist: an annexe is built to a residential standard, so most are built by companies offering a turnkey service, from design and approval to groundworks, the build, connections and sign-off.
- Two routes to approval: full planning permission with Building Regulations, or the Caravan Act, usually building to BS3632 and confirming the position with a Lawful Development Certificate.
- Timescales: allow 6–12 months from application to moving in on the full planning route. The Caravan Act route is often faster: around 3–6 months from first contact to moving in on projects featured on the Guide.
- The budget: the building, plus around £15,000–£20,000 for groundworks and mains connections where they aren’t included in the price.
Decide who it is for, and what it needs to do
Start with the person who will live there, not the building. An annexe for an older parent needs level access, wide doorways and a walk-in shower designed in from the start. An adult child may want more storage and a proper desk. Guests need less kitchen. These decisions set the layout and the size, and the size sets most of the cost.
Check the site
Three things decide what a garden can take, and a builder’s site survey will look at all of them.
- Space and position
- How far the annexe sits from the house, from boundaries and from trees, and how it will look from the house and from the neighbours. Booths Garden Studios’ one-bedroom annexe in the garden of a three-bed end-of-terrace shows a modest garden can work when the height and materials are chosen carefully.
- Access
- How the building, or its panels or sections, will get into the garden. A narrow side passage changes how an annexe can be built and delivered.
- Services and levels
- How far the water, drainage and power have to run, and how much the ground slopes. Executive Garden Rooms’ annexe for a son sat 60 metres from the house on a sloping plot, which meant a 60-metre trench to the mains and a reinforced slab.
Choose the planning route
A self-contained annexe never falls under Permitted Development, so it needs either planning permission or to qualify as a caravan. There are two routes.
- Full planning permission with Building Regulations
- A planning application to the local authority, then a building signed off by Building Control. It is a permanent building with planning permission, and usually carries VAT at 20%.
- The Caravan Act
- The annexe is built as a twin-unit caravan, usually to BS3632, the residential park home standard, and used in connection with the house. There is no planning application; a Lawful Development Certificate confirms that the siting is lawful. It may qualify for zero-rated VAT.
Some specialists apply on both routes at once where a site is uncertain. Annexe Spaces offered that dual approach on a future-proofed annexe built under the Caravan Act.
Set the budget
A compact studio starts from about £50,000, a one-bedroom annexe typically costs £70,000–£120,000 and a two-bedroom £125,000–£160,000 or more, and up to about £190,000 on the full planning route. Some companies include foundations in the price, and a few include a short run of services, usually 10m to 20m. Connecting to the water, drainage and electrics at the house beyond that is normally extra. Where neither is included, groundworks and connections typically add £15,000–£20,000.
When comparing quotes, check what each one includes. The items most often left out are the connections to the house, any groundworks the price doesn’t cover, planning and Building Control fees, VAT, reinstating the garden afterwards, and a data cable for broadband.
Choose the builder and the design
Most buyers choose a specialist that handles the whole project, from planning to handover. Some prefer to buy the building from a specialist and organise the groundworks, electrician and plumber themselves. That can work, but it needs to be clear from the start where the builder’s responsibility ends and yours begins.
The design stage turns the brief into drawings: the layout, where the doors and windows go, the kitchen and bathroom, and how the annexe relates to the house and the garden. Standard ranges can usually be adapted. Bespoke designers work to the exact space the garden allows.
- How many annexes have you completed in the last two years, and can I visit one?
- Which planning route do you use, and why is it right for my site?
- Who prepares the planning application or the Lawful Development Certificate, and who handles sign-off?
- Does the price include the groundworks, the connections and VAT?
Get approval
Who handles it. Many annexe specialists take care of the planning application or the Lawful Development Certificate as part of their service, using an in-house planning expert or a consultant they work with regularly. If yours does not, or you want independent advice before choosing a builder, you can appoint a planning consultant yourself. The Guide’s planning specialists page lists firms that handle garden room and annexe applications.
On the full planning route, the application goes to the local authority, which normally has eight weeks to decide a valid application, longer if you agree an extension. Building Regulations approval follows alongside. On the Caravan Act route, the Lawful Development Certificate application sets out why the building meets the definition of a caravan and how it will be used. Nothing should be built until the approval is in place.
Groundworks, foundations and services
Before the building arrives, the ground is prepared and the services are laid.
- Foundations
- Ground screws are widely used. Steel piles are screwed into the ground and adjusted individually, which suits sloping sites and leaves no concrete. Ark Design Build used a ground-screw foundation to level a 42sqm annexe on a significant slope in Tunbridge Wells, with the cladding carried down to hide it. Some companies prefer a concrete slab, which leaves no void under the building.
- Services
- Trenches carry water, drainage, power and a data cable from the house. Some sites also need a pumping system for the drainage, as on Executive Garden Rooms’ one-person annexe.
The garden will look worse before it looks better. On Executive Garden Rooms’ annexe for a son, the lawn had recovered within eight weeks of completion.
The build
How long the building takes on site depends mostly on how much is made off site.
- Factory-made frames and panels
- These go up quickly. Garden Annexes’ team erected the full timber frame of an Annexxa 745 in a single day, with the foundations and service routes already in place, and the team assembles and commissions an annexe in a few days once the groundworks are in.
- Panel systems assembled on site
- These take a few weeks. Swift Unlimited test assemble every building in the factory before it reaches the garden, numbering the panels, so the on-site phase runs to a few weeks.
- Buildings constructed on site
- These take longer, with more trades and more weather to work around.
Inside, the work moves through first fix, the wiring and pipework in the walls, then plastering, then second fix: the kitchen, bathroom, sockets and lights.
Sign-off, connections and moving in
Before anyone moves in, the building is signed off. On the full planning route that means Building Control completion. On the Caravan Act route it usually means the manufacturer’s BS3632 certification, with the Lawful Development Certificate already in hand. Keep both with the property’s paperwork; buyers, lenders and the council can all ask for them.
Then tell the council. A self-contained annexe can be given its own council tax band, but discounts and exemptions may apply depending on who lives there.
How long does it take to build a granny annexe?
| Stage | Full planning permission | Caravan Act |
|---|---|---|
| Design and site survey | A few weeks | A few weeks |
| Approval | Planning decision, usually 8 weeks for a valid application | Lawful Development Certificate, usually 8 weeks |
| Groundworks and services | 1–3 weeks, longer on difficult sites | 1–3 weeks |
| The build and fit-out | A few days to several weeks, depending on the system | A few days to several weeks |
| Typical total | 6–12 months from application to moving in | Often faster: around 3–6 months from first contact to moving in |
Annexe Spaces delivered their future-proofed Caravan Act annexe move-in ready in about 12 weeks. Booths Garden Studios had a client living in her annexe within six months of first contact, including approval, which took under seven weeks.
Find annexe specialists working in your part of the UK
Please select your location to search.
Official guidance
This page explains the rules in plain English. The official wording is in these sources, and where a council takes a different view of a particular case, the council decides, subject to appeal. An experienced annexe designer will walk you through the routes at the design stage, and planning consultants can advise where a site is less straightforward. But as the householder, it’s your responsibility to confirm your own position.
- Permitted development rights for householders: Technical Guidance
- Why a bedroom, a kitchen or a bathroom isn’t covered by the Permitted Development rules for garden buildings (Class E).
- Caravan Sites Act 1968, section 13
- Twin-unit caravans: no more than two sections, movable by road once assembled, and the 20m × 6.8m × 3.05m limits.
- Lawful development certificates (GOV.UK guidance)
- What a certificate confirms, how to apply and how long the council has to decide.
- Building Regulations 2010, Schedule 2
- The exemptions for small buildings, which don’t apply where there’s sleeping accommodation.
- Planning fees in England (GOV.UK)
- The current fee schedule for planning applications and certificates.
Frequently asked questions
- How long does it take to build a granny annexe?
- On the full planning route, allow 6 to 12 months from the planning application to moving in. The Caravan Act route is often faster: on projects featured on the Guide, around three to six months from first contact to moving in. Once the groundworks are done, a factory-made annexe can be installed in a few days.
- Can I build a granny annexe in my garden?
- In most gardens, yes, if there is room for the building, access to get it in, and a way to connect water, drainage and power. It needs either full planning permission with Building Regulations, or to qualify under the Caravan Act route, usually confirmed by a Lawful Development Certificate.
- Do I need planning permission to build a granny annexe?
- A self-contained annexe can’t be built as an ordinary garden building. It needs either full planning permission with Building Regulations, or to qualify under the Caravan Act route, where the annexe is usually built to BS3632 and a Lawful Development Certificate confirms the siting is lawful.
- How much does it cost to build a granny annexe?
- A compact studio starts from about £50,000, a one-bedroom annexe typically costs £70,000–£120,000 and a two-bedroom £125,000–£160,000 or more. Where they aren’t included, groundworks and mains connections typically add £15,000–£20,000.
- What are the rules on annexes?
- Most annexes are approved or sited for use in connection with the main house, by family, guests or a member of the household, rather than as a separate home, and that then has to hold. It is built for year-round living (Building Regulations, or usually BS3632 on the Caravan Act route), and its route is settled before it is built.